Located at the intersection Beresford Street and McKay Avenue in Burnaby, BC the excavation and shoring for the two towers of the Gold House project was completed in 2 phases over 18 months.  The excavation and shoring for the Gold House project in Burnaby included 99,500m³ of excavation and 5,706m² of shotcrete. 

PROJECT SUMMARY

Owner: Rize Alliance

Completion: August 2017

Engineer: GeoPacific Consultants Ltd.

SWC Supervisor: Jeff Fletcher / Dave Martin

SCOPE OF WORK

Excavation Volume: ~99,500 m³ (4,000 m³ of detailed excavation)

Excavation Depth: 18m

Shoring Wall Area: 5,706m²

Shoring Anchors: 1,675 anchors totaling 18,000m of anchors.