Located at 603-607 Regan Avenue, Coquitlam, excavation and shoring was completed in 3 months. The project included 16,000 m³ of excavation of material, 1,000 m² of shoring and 2,300 m of anchors.

PROJECT SUMMARY

Owner: Marcon Developments Ltd.

General Contractor: Marcon Construction Ltd.

Completion: October 2018 Engineer:

GeoPacific Consultants Ltd.

SWC Supervisor: Phil Brisette / Dave Martin