Excavation and Shoring – The Stanton Located at 2089 West 43rd Avenue, Vancouver, this project included the installation of rakers and walers to support the north wall due to having no encroachment. Bulk excavation and shoring was completed on schedule in September 2017.

PROJECT SUMMARY

Owner: Landmark Premiere Properties Ltd.

General Contractor: Syncra Construction Corporation

Completion: September 2017

Engineer: GeoPacific Consultants Ltd.

SWC Supervisor: Bryan Thomson / Dave Martin

Excavation and Shoring – The Stanton Excavation and Shoring – The Stanton