PROJECT SUMMARY

Owner: Wesbild Holdings Ltd.

General Contractor: Gemco Construction

Completion: October 2015

Engineer: Golder Associates / InterCAD

SWC Supervisor: Dave Martin  

SCOPE OF WORK

1,375m² of permanent rock carved shotcrete

487 permanent hollow core anchors (5,300m of anchors total)  

PROJECT DESCRIPTION

The Partington Creek development on Burke Mountain in Coquitlam required a number of retaining walls to be constructed for the development.  The retaining walls consisted of Allen Block Walls, Stone Strong Walls and permanent shotcrete retaining walls.

On the project Southwest Contracting Ltd (SWC) installed 3 permanent retaining walls as part of 2 different phases of the overall development.  The permanent retaining wall H consisted of permanent DCP anchors with a 200mm thick temporary shotcrete facing.  Once the temporary shotcrete facing was installed it was overlaid with a permanent architectural shotcrete facing.  The client for this project specified a natural rock look for the permanent shotcrete.

Permanent Shotcrete Retaining Wall - Burke Mountain Retaining Wall H Permanent Shotcrete Retaining Wall - Burke Mountain Retaining Wall H Permanent Shotcrete Retaining Wall - Burke Mountain Retaining Wall H