Ruskin Dam Generating Station
Project Description
PROJECT SUMMARY
Approximate Shoring Contract Value: $720,000
Engineer: BC Hydro
SCOPE OF WORK
- Rock anchors: 16 anchors, 26dia. 1035MPa threadbar with DCP x 7.5m ea.
PROJECT DESCRIPTION
As part of the BC Hydro – Ruskin Dam and Powerhouse Upgrade Project, SWC undertook the installation of 16 rock anchors for intakes 1 and 2. The anchors were designed to increase the structural stability of the existing intakes, such that they can resist sliding and toppling movements during a seismic event.
The anchors had to be drilled through the existing deck, through water, and to the bedrock. Contact pipes were installed prior to mobilization, to facilitate a sealed environment for SWC to install the anchors through. SWC had to check the seal by conducting pressure tests; if the test failed, the contact pipe had to be grouted, re-drilled, and the seal re-checked. SWC worked with divers, who assisted with setting the installation of hardware underwater.
Project Details
DATE
October 1, 2015
General Contractor
Flatiron-Dragados Joint Venture
CLIENT
Flatiron-Dragados Joint Venture
LOCATION
Mission, BC
PROJECT MANAGER
Will Pauga
PROJECT TYPE
Project Gallery
CONTACT US
Ask us how we can work together to advance your heavy construction goals. From shotcrete shoring, jet grouting and bulk excavation, to underground utility installation, road building, hydraulic drilling for tiebacks, seismic anchors, and micropiles, SWC is synonymous with quality, reliability and innovation.