Ruskin Dam Generating Station

Project Description

PROJECT SUMMARY

Approximate Shoring Contract Value:  $720,000
Engineer: BC Hydro

SCOPE OF WORK

  • Rock anchors: 16 anchors, 26dia. 1035MPa threadbar with DCP x 7.5m ea.

PROJECT DESCRIPTION

As part of the BC Hydro – Ruskin Dam and Powerhouse Upgrade Project, SWC undertook the installation of 16 rock anchors for intakes 1 and 2. The anchors were designed to increase the structural stability of the existing intakes, such that they can resist sliding and toppling movements during a seismic event.

The anchors had to be drilled through the existing deck, through water, and to the bedrock. Contact pipes were installed prior to mobilization, to facilitate a sealed environment for SWC to install the anchors through. SWC had to check the seal by conducting pressure tests; if the test failed, the contact pipe had to be grouted, re-drilled, and the seal re-checked. SWC worked with divers, who assisted with setting the installation of hardware underwater.

 

Project Details

DATE

October 1, 2015

General Contractor

Flatiron-Dragados Joint Venture

CLIENT

Flatiron-Dragados Joint Venture

LOCATION

Mission, BC

PROJECT MANAGER

Will Pauga

PROJECT TYPE

Project Gallery

CONTACT US

Ask us how we can work together to advance your heavy construction goals. From shotcrete shoring, jet grouting and bulk excavation, to underground utility installation, road building, hydraulic drilling for tiebacks, seismic anchors, and micropiles, SWC is synonymous with quality, reliability and innovation.

CONTACT US