VGH: Academic Ambulatory Care Centre

Project Description

This P3 project was on a critical timeline. Very dense layers of siltstone and sandstone for the full depth of 50’ were difficult to penetrate, posing a major challenge to excavators. However, the concrete formwork did start on time and project schedule was maintained despite this difficulty.

The 120,000lb excavator, instrumental to the success of this project, was lifted out of the excavation upon completion.

Scope of work

  • Excavation Volume: ~ 105,000 cubic yards
  • Shotcrete Anchors: 776 ea x ~25’ = 19,700 Ft
  • Shotcrete Shoring Wall Area: 42,800 sq. feet

Project Details

DATE

May 1, 2005

CLIENT

PCL Westcoast Constructors Inc.

LOCATION

Vancouver, BC

PROJECT TYPE

Project Gallery

CONTACT US

Ask us how we can work together to advance your heavy construction goals. From shotcrete shoring, jet grouting and bulk excavation, to underground utility installation, road building, hydraulic drilling for tiebacks, seismic anchors, and micropiles, SWC is synonymous with quality, reliability and innovation.